HET End-Trimester Report
Third Period of 2004
August 1 - November 30

This report is composed of five sections:
Facility Status

In this section we will discuss the status of the HET facility and each instrument and any limitation to configurations that occurred during the period.

  • Tracker: FIF IC for 4 days followed by 12 days of PFIP and LRS engineering.

  • LRS: LRS was run with G3 for the first days of the period; we have switched between G3 and G2 on schedule as required by the queue. The LRS guide camera was realigned along with the LRS pick off mirror during the PFIP engineering.

  • SAMS and MARS: SAMS and MARS were run during the entire period. Mirror recoating has caused some strain on the SAMS system with nearby poorly constrained mirrors moving out of the stack during the night. This has lead to more frequent restacking. SAMS engineering Nov 15-Nov 18 but had no impact on science operations.

  • HRS: The HRS was down 14 days due to the FIF IC and PFIP Engineering. The HRS lost cooling from the cryotiger on one night but was brought back online before the end of the night to resume science. On Oct 28th the FIF fibers were found to move relative to the guide star on the Acq system. The magnitude is about .9" per 20 minutes. We have limited exposure times and reaquired the fibers between exposures to continue operations until this problem can be diagnosed and fixed

  • MRS: The MRS was down from 16 Aug until the report was written for FIF IC then the PFIP take down and lastly a problem with cooling the CCD electronics. The electronics unit was shipped back after analysis by Leach. The MRS was then brought back on-line and science resumed until the MRS CCD vacuum failed on Oct 31. The MRS remained offline from Oct 31 to Nov 30. On Oct 28th the FIF fibers were found to move relative to the guide star on the Acq system. The magnitude is about .9" per 20 minutes. We have limited exposure times and reaquired the fibers between exposures to continue operations until this problem can be diagnosed and fixed

  • Instrument Commissioning: During this period there was some FIF and MRS IC which also caused HRS to be down during these 4 days. Most of those days were foggy.

  • Engineering: There were been 93.2 dedicated hours for Engineering, most of which was work on the PFIP and LRS while on the ground. 30 of these hours were lost due to weather.
    Observing Statistics

    NOTE: We are now using FWHM which is measured off both the LRS "pre" images and the FIF bent prime guider.

    The following image quality statistics were taken from the statistics recorded for science operations in the night report.

    For comparison here is the image quality for the same period of 2003

    Here are the DIMM values reported in the night report.

    Month by Month Summary

    The following table gives the observing statistics for each month. The second column gives the fraction of the month that was spent attempting science (as opposed to engineering or instrument commissioning). Science time is defined to begin at 18 degree twilight or the first science target. Science time is defined to end at 18 degree twilight or the last science target. The fourth column gives the fraction of the possible science time (A) lost due to weather. The fifth through tenth columns give how the remaining science time (after removing weather losses) was spent. Please note that the first stack of the night often occurs before 18 degree twilight.

    Month A:Fraction of the Time that was Possible Science B:Average Night Length C:Fraction of Total Science Time Lost due to Weather D:Fraction of Actual Science Time with Shutter Open E:Fraction of Actual Science Time as Overhead F:Fraction of Actual Science Time Lost due to Alignment G:Fraction of Actual Science Time Lost due to Calibrations H:Fraction of Actual Science Time Lost due to Problems I:Fraction of Actual Science Time Not accounted for or Lost
    August 0.716 7.92 0.41 0.48 0.34 0.05 0.03 0.05 0.04
    September 0.857 8.99 0.53 0.53 0.32 0.05 0.02 0.02 0.07
    October 0.956 9.93 0.54 0.50 0.36 0.04 0.02 0.04 0.04
    November 0.964 10.63 0.56 0.43 0.32 0.04 0.03 0.10 0.08

    The last column is new and acounts for all of the lost or not used minutes. Some of this time is accounting errors and some is time not charged to any program due to operations inefficiency.

    Details on Nightly cloud cover based on the TO's observations of the sky reported 3 times a night in the night report.:

    Month Fraction of the Nights that were Clear Fraction of the Nights that were Mostly Clear Fraction of the Nights that were Partly Cloudy Fraction of the Nights that were Mostly Cloudy Fraction of the Nights that were Cloudy
    August 0.16 0.10 0.23 0.07 0.13
    September 0.20 0.00 0.13 0.10 0.17
    October 0.16 0.10 0.22 0.10 0.39
    November 0.30 0.03 0.20 0.17 0.23

    Please note that the HET could be closed due to humidity, smoke or high dust count and still have a "Clear" statistic in the night report.

    The following tables give a break down of all attempted visits as well as the category that each falls into.

    Charged exposures
    Number of TimesShutter Open (Hours)Type
    1105184.4 A - Acceptable
    4911.3 B - Acceptable but Border line conditions
    26534.8 4 - Priority 4 visits (does not include 1/2 charge)
    00.0 Q - charged but PI error
    00.0 C - Acceptable by RA but PI rejects

    Uncharged exposures
    Number of TimesShutter Open (Hours)Type
    90.7 I - Targets observed under otherwise idle conditions
    40.9 E - Rejected by RA for Equipment Failure
    294.7 H - Rejected for Human failure
    10114.3 W - Rejected by RA for Weather
    162.4 P - Rejected by PI and confirmed by RA
    141.2 N - Rejected due to unknown cause

    So this is a total of 24.2 hours of uncharged spectra with an additional possible 11.3 hours of spectra that might have been rejected.

    The following overhead statistics include slew, setup, readout and refocus between exposures (if there are multiple exposures per visit). In the summary page for each program the average setup time is calculated. The table below gives the average setup time for each instrument PER VISIT and the average and maximum COMPLETED science exposures and visits.

    The "Exposure" is defined by when the CCD opens and closes. A "Visit" is the requested total CCD shutter open time during a track and might be made up of several "Exposures". "Visit" as defined here contains no overhead. To calculate one type of observing efficiency metric one might divide the "Visit" by the sum of "Visit" + "Overhead".

    The average overhead per actual visit is the overhead for each acceptable priority 0-3 (not borderline, and with overheads > 4 minutes to avoid 2nd half of exposures with unrealisticly low overheads) science target. This number reflects how quickly we can move from object to object on average for each instrument, however, this statistic tends to weight the overhead for programs with large number of targets such as planet search programs.

    The average overhead per requested visit is the total charged overhead per requested priority 0-3 visit averaged per program. To get this value we average the average overhead for each program as presented in the program status web pages. The average overhead per visit can be inflated by extra overhead charged for PI mistakes (such as bad finding charts or no targets found at sky detection limits) or for incomplete visits e.g. 2 visits of 1800s are done instead of 1 visit with a CRsplit of 2. The average overhead per visit can be deflated by the 15 minute cap applied to the HRS and MRS. This method tends to weight the overhead to programs with few targets and bad requested visit lengths, ie. very close to the track length.

    Instrument Avg Overhead per Actual Visit(min)Avg Overhead per Requested Visit(min) Avg Exposure (sec)Median Exposure (sec)Max Exposure (sec)Avg Visit (sec)Median Visit (sec)Max Visit (sec)
    LRS 13.3 15.1 682.5 600 1800 1121.36004320
    HRS 11.1 11.7 645.1 600 3600 779.26604500
    MRS 26.5 20.0 553.3 900 900 2133.327002700

    NOTE: AS OF 2003-3 THE SETUP TIME FOR AN ATTEMPTED MRS OR HRS TARGET IS CAPPED AT 15 MINUTES.

    NOTE: AS OF 2004-3 THE SETUP TIME FOR AN ATTEMPTED LRS TARGET IS CAPPED AT 20 MINUTES.

    The overhead statistics can be shortened by multiple setups (each one counted as a separate visit) while on the same target as is the case for planet search programs. The overhead statistics can be lengthened by having multiple tracks that add up to a single htopx visit as can happen for very long tracks where each attempt might only yield a half visit.

    A way to improve the overhead accumulated for programs with long exposure times is to add double the above overhead to the requested visit length and make sure that time is shorter than the actual track length. This avoids the RA having to split requested visits between several different tracks.



    The following is a histogram of the current HET queue visits for the rest of the period. A line has been drawn at the expected number of hour long visits that we hope to achieve in each hour bin.

    The following histogram shows some of the extrema in observing conditions: good seeing dark time, bright time and bad seeing dark time. A line has been drawn at the expected number of hour long visits that we hope to achieve in each hour bin.

    The following histogram shows the bright time priority 0-3 contribution from each partner. The dashed line is a rough estimate of the number of hour long visits one could complete during the remainder of the period.

    The following histogram shows the dark time priority 0-3 contribution from each partner. The dashed line is a rough estimate of the number of hour long visits one could complete during the remainder of the period.

    The following histogram shows the use of LRS_g2 vs. LRS_g3 for priority 0-3 programs in this period.

    From the above plots I have determined that:

    • Most of the remaining high priority targets are G2 or G3
    • Weather really hurt our completion rates.
    • As mentioned in the beginning of trimester report the Munich targets were not likely to be completed and they were not.


    Observing Programs Status

    The following links give the summary for each institution and its programs. The resulting table will give (for each program) the total number of targets in the queue and the number completed, the CCD shutter open hours, average overhead for that program, and the TAC allocated time. This usually will be the best metric for judging completeness but there are times when a PI will tell us that a target is "done" before the total number of visits is complete.

  • PSU Data
    Program comments:
    Including MRS programs and factoring submitted targets, Completion Rates are: P0 = 100%, P1 = 86%, P2 = 94%, P3 = 67%

  • STA Data
    Program comments:
    Including MRS programs and factoring submitted targets, Completion Rates are: P0 = 50%, P1 = 70%, P2 = 100%, P3 = 60%

  • MUN Data
    Program comments:
    Including MRS programs and factoring submitted targets, Completion Rates are: P0 = 100%, P1 = 82%, P2 = 100%, P3 = 0%

  • G Data
    Program comments:
    Including MRS programs and factoring submitted targets, Completion Rates are: P0 = 100%, P1 = 100%, P2 = 100%, P3 = 100%


    Institution Status

    This is how each institution has allocated its time by priority.

    Time Allocation by Institution (hours)
    Institution Priority 0 Priority 1 Priority 2Priority 3 Priority 4
    PSU 7.000 (6%) 25.220 (21%) 25.480 (21%) 15.000 (12%) 49.960 (41%)
    UT 18.000 (8%) 66.500 (29%) 65.750 (29%) 48.000 (21%) 28.000 (12%)
    Stanford 4.000 (11%) 6.000 (17%) 10.000 (29%) 10.000 (29%) 5.000(14%)
    Munich 0.000 (0%) 5.000 (50%) 0.000 (0%) 5.000 (50%) 0.000 (0%)
    Goetting 0.000 (0%) 1.000 (8%) 12.000 (92%) 0.000 (20%) 0.000 (0%)
    NOAO 0.000 20.000 37.500 15.000 0.000
    SALT 0.000 0.000 0.000 0.000 0.000
    DDT 0.000 0.000 0.000 0.000 0.000



    The following is a summary of the Acceptable CCD shutter time for each institution based on our night report data base. It does not include any overhead. Priority 4 time is charge at 0.5 of the visits completed.

    CCD shutter Open by Institution (hours)
    -TOTAL- Used % of All
    PSU 44.18 23.0
    UT 118.99 60.9
    Stanford 22.33 11.4
    Munich 2.67 1.4
    Goetting 7.34 3.8
    NOAO 14.81 --
    SALT 0.00 --
    DDT 0.00 --

    The following is a summary of the total charged time for each institution based on our htopx data base (for shutter open) and night reports (for overhead). It includes shutter open time and overhead. Priority 4 time is charged at half its normal rate and without overhead.

    Time Charged by Institution (hours)
    -INST- Used % of All -TOTAL TO DATE- -% TO DATE-
    PSU 62.88 21.8 969.728.9
    UT 178.37 61.9 1901.956.7
    Stanford 30.39 10.6 237.9 7.1
    Munich 4.09 1.4 111.73.3
    Goetting 12.33 4.3 132.84.0
    NOAO N/A -- -- --
    SALT 0.00 -- -- --
    DDT 0.00 -- -- --


    Total to Date starting from Oct 1999.

    TAC Response