TO Projects
Note that most projects should be commissioning related at the present time.
{{{#!== Chevo ==
- Optics Team laptop and SCS hardware interface - ongoing.
- CCAS POV camera project - ongoing.
- Video Server upgrade and repairs - ongoing.
- Video cameras for in dome VSS research. - ongoing.
- Video Production - Ongoing as needed.
- Research for Spectrograph Room lighting upgrade. - ongoing.
- Zoom video conference install in control room. - finished.
- Microphone install for Zoom video conference. - finished.
- Seating upgrade to control room. - finished.
- Seating upgrade for LER. - finished.
Ideas
- Remote activate and control DIMM louvers and Shutter.
- Remote control Dome enclosure Louvers.
}}}
Amy
- TO report functions (input from other TOs welcome)
- Metrics data miner
Justen
- DIMM - Maintenance of DIMM system
- Updating the HET blog (posting when I have information and going through comments)
- CCAS insulation/radiant barrier (in testing/proposal phase)
- Changing PV analysis over to points on Sphere.
- Ubuntu Science Support
- Interim Resident Astronomer
{{{#!== Emily ==
- Continue to updated TO manual as needed. (Finished for now)
- Continue to update OPS manual as needed. (Finished for now)
- Gather metrics for reviews. (Finished for 2017 - 2018)
- Overlap metrics for reviews. (Finsihed for 2017 - 2018)
- Photograph interior of VIRUS spectrographs to track signs of wear on fibers. (Ongoing)
- Gather RSE/HEFI post observing metrics. (Finished for 2017 - 2018)
- Clean AZ coil. (Ongoing. Last completed March 2018)
- Assist Justen with CCAS insulation/radiant barrier.
- Probe Position Data. (Finished. 2017)
- Update message on warning sign for dome entry. (Finished.2017)
- Emergency Shut down on telescope for RA. (Text finished. Will be adding images for additional information)
- GOES16 long term visual. (Initial stages) }}}